Short circuit or Full Load Test of Transformer A power transformer is usually employed for the purpose of converting power, at a Fixed frequency, from one voltage to another. If it is used for converting power from a high voltage to a low voltage, it is called a step-down transformer. The conversion efficiency of a power transformer is extremely high and almost all of the input power is supplied as output power at the secondary winding. For confirming the specifications and performances of an electrical power transformer it has to go through Short Circuit Test (Full load test) on the Transformer. In this video, we will learn about short circuit test and their procedure. More videos:- Transformer Testing | Transformer Testing and their Procedure https://youtu.be/KOH1TVf1EuY Types of Faults in Power System | Fault In Electrical Transmission Line https://youtu.be/S58rOwYvXwg Types of Circuit Breaker | Classification of Circuit Breaker | Circuit Breaker https://youtu.be/UMCaRjk1ZYU #TransformerTesting #ShortCircuitTest #Learning_Engineering #konok_kamruzzaman Follow me on Facebook: https://www.facebook.com/Learning.Engring Join my Facebook group: https://www.facebook.com/groups/1913745875521183/ Dear Sir, Thanks for watching my videos. If you have any questions write in the comment box. Don’t forget to like and share. For more updates please subscribes to our channel Learning Engineering, and get a notification to press the bell icon.


NEXT ARTICLE Next Post
PREVIOUS ARTICLE Previous Post
NEXT ARTICLE Next Post
PREVIOUS ARTICLE Previous Post